Residents Association Councillor, Andrew Mann (Havering Park) has learnt of plans by Transport for London to open the flyover this week, but only one way ! And it may take over a year to re-open fully, if ever.
The planned re-opening of the flyover was originally set for 2nd June; this was delayed until 28th July because an inspection had identified the need for further works. However, it has now been discovered by engineers that even more work is required, involving the steel-railed safety barriers on the flyover, as they are unsafe and will require new barriers to be installed.
However, this work can not be completed with a two way traffic flow and from next Monday (28th July), the flyover will operate in only the London Bound (Westward) direction for the foreseeable future. It can not be confirmed at the moment how long this situation will prevail, it has been suggested it could be well over 12 months, but maybe even longer.
Cllr Mann said “This situation is going from bad to worse, the flyover has already been closed for months causing misery to local residents and commuters, I find it unbelievable in this day and age, that engineers could not have surveyed the structure in more detail before they started the works”.
However, Cllr Mann is now worried about the future of the flyover he said “We all know that this flyover was moved form another location and installed over 35 years ago as a temporary structure, for years it has been allowed to sit and rot with no major maintenance work on it, TfL have failed to look after it properly until it is to late”.
He went on, it has been suggested to me by a reliable source that the flyover works set to take 12 months might be delayed even longer, as when they start on the new barriers, it may well unearth even more rust and damage that will make it unsafe for ever and nothing but scrap metal, to that end I will be writing to Mayor of London Boris Johnson and TfL Head, Peter Hendy, asking them both to set out precise plans for the re-opening of the flyover in both directions as a matter of urgency”
The planned re-opening of the flyover was originally set for 2nd June; this was delayed until 28th July because an inspection had identified the need for further works. However, it has now been discovered by engineers that even more work is required, involving the steel-railed safety barriers on the flyover, as they are unsafe and will require new barriers to be installed.
However, this work can not be completed with a two way traffic flow and from next Monday (28th July), the flyover will operate in only the London Bound (Westward) direction for the foreseeable future. It can not be confirmed at the moment how long this situation will prevail, it has been suggested it could be well over 12 months, but maybe even longer.
Cllr Mann said “This situation is going from bad to worse, the flyover has already been closed for months causing misery to local residents and commuters, I find it unbelievable in this day and age, that engineers could not have surveyed the structure in more detail before they started the works”.
However, Cllr Mann is now worried about the future of the flyover he said “We all know that this flyover was moved form another location and installed over 35 years ago as a temporary structure, for years it has been allowed to sit and rot with no major maintenance work on it, TfL have failed to look after it properly until it is to late”.
He went on, it has been suggested to me by a reliable source that the flyover works set to take 12 months might be delayed even longer, as when they start on the new barriers, it may well unearth even more rust and damage that will make it unsafe for ever and nothing but scrap metal, to that end I will be writing to Mayor of London Boris Johnson and TfL Head, Peter Hendy, asking them both to set out precise plans for the re-opening of the flyover in both directions as a matter of urgency”